Resources / OEE
Free calculator
OEE calculator
Enter the planned production time, the downtime, the ideal cycle time and the pieces produced. The calculator returns the three OEE factors and shows which one loses the most.
In short
OEE (Overall Equipment Effectiveness) is the share of planned production time that turns into good parts at the ideal speed. It is the product of availability, performance and quality.
The formula
Run time is planned time minus downtime. The ideal cycle time is entered in seconds and converted to minutes before it is compared with run time.
The six big losses and the factor they reduce
| Loss | OEE factor | Typical examples |
|---|---|---|
| Breakdowns | Availability | Equipment failure, unplanned maintenance |
| Setups and adjustments | Availability | Changeovers, warm-up, waiting for material |
| Short stops | Performance | Jams, sensor trips, brief clearing |
| Reduced speed | Performance | Running below the rated speed |
| Start-up rejects | Quality | Scrap while the process settles |
| Production rejects | Quality | Scrap and rework during steady running |
Worked example
A machine is planned for 480 minutes and stops for 60, so it runs 420 minutes: availability is 87.5%. At an ideal 30 seconds per piece, the 700 pieces produced need 350 minutes, so performance is 83.3%. Of those 700 pieces, 665 are good: quality is 95%. OEE = 87.5% × 83.3% × 95% = 69%, and the largest loss is performance.
Related guides
Frequently asked questions
What is a good OEE?
It depends on the process and on how strictly downtime and ideal cycle time are defined. Compare a machine with itself over time, using the same definitions, rather than with a figure from elsewhere.
Is planned maintenance counted as downtime?
Usually not: time with no production planned is left out of planned production time. What matters is applying the same rule every time the OEE is calculated.
What is the difference between OEE and availability?
Availability only measures how long the machine ran compared with what was planned. OEE also counts how fast it ran and how many of the pieces were good.
Run the whole project in one place
Charter, SIPOC, KPIs, causes, actions and control plan linked, with an AI copilot that drafts the first version.
COOKIES
LeanOS uses cookies and browser storage to work.
We only store what the site needs: your sign-in, your language and your settings. With your permission we also use Google Analytics to see how the website is used; it stays off unless you turn it on. You can change your choice at any time under Cookie preferences. Cookie policy · Privacy policy